Diriyah 2
Phase 2 bulk excavation
The published section below is public fact with a source. Everything in the delivery section is an illustrative demonstration record.
Published construction award
Public factSAR 759m
As announced; not a live approved budget.
Announced
Public fact17 Dec 2024
Announcement date as published.
Named child assets
Public fact1
Children of one parent award. None carries an independent published budget.
Illustrative records joined here
Scenario30
Across schedule, documents, field, commercial, procurement and risk.
Published scope and parties
- Bulk excavation across approximately 6.3 km² of phase 2
Parties as publishedChina Harbour Engineering Company
Child assets
Named components of the parent award. Values are never split or invented for children.
| Asset | Treatment | Independent budget |
|---|---|---|
| Approx. 6.3 km² excavation area | Published scope component; no separate value. | None published |
Illustrative cashflow shape
Scenario planned versus recorded actual. Demonstration values only.
Scenario control budget
ScenarioSAR 759m
Scenario committed
ScenarioSAR 472m
Scenario certified
ScenarioSAR 309m
Scenario EAC
ScenarioSAR 757m
Illustrative delivery position
Records are joined by ID across the Asite product set.
| Record | Reference | Status | Captured in | Open |
|---|---|---|---|---|
| Milestone | MS-G-EXC-1 · Enabling works completion | on track · forecast 12 Oct 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-EXC-2 · Primary structure topping out | at risk · forecast 21 Jan 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-EXC-3 · Facade first panel installed | slipping · forecast 17 Mar 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-EXC-4 · MEP first fix complete | at risk · forecast 23 Feb 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-EXC-5 · Vertical transportation energisation | at risk · forecast 23 Apr 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-EXC-6 · Landscape hard works complete | on track · forecast 4 Jul 2027 | Asite PMIS | Readiness |
| Document | DOC-EXC-100 · General arrangement plan — level 01 rev A01 | under review | Asite CDE | Register |
| Document | DOC-EXC-101 · Structural frame details — grid F rev B02 | under review | Asite CDE | Register |
| Document | DOC-EXC-102 · MEP services coordination model extract rev C03 | approved with comment | Asite CDE | Register |
| Document | DOC-EXC-103 · Facade bracket and anchor details rev A04 | under review | Asite CDE | Register |