Diriyah 1 — hospitality cluster
Waldorf Astoria Superblock
The published section below is public fact with a source. Everything in the delivery section is an illustrative demonstration record.
Published construction award
Public factSAR 2.73bn
As announced; not a live approved budget.
Announced
Public fact30 Jul 2026
Announcement date as published.
Named child assets
Public fact3
Children of one parent award. None carries an independent published budget.
Illustrative records joined here
Scenario30
Across schedule, documents, field, commercial, procurement and risk.
Published scope and parties
- Published categories: 160 rooms, 39 suites, 1 presidential suite, 47 residences
- Hotel GFA 22,715 sqm
- Residences GFA 10,090 sqm
- Offices 45,000+ sqm
Parties as publishedHassan Allam Construction Saudi · Urbacon Trading & Contracting
Child assets
Named components of the parent award. Values are never split or invented for children.
| Asset | Treatment | Independent budget |
|---|---|---|
| Hotel — 160 rooms, 39 suites, 1 presidential suite | Categories preserved exactly as published; not summed. | None published |
| 47 residences (GFA 10,090 sqm) | Published scope component; no separate value. | None published |
| Offices, 45,000+ sqm | Published scope component; no separate value. | None published |
Illustrative cashflow shape
Scenario planned versus recorded actual. Demonstration values only.
Scenario control budget
ScenarioSAR 2.73bn
Scenario committed
ScenarioSAR 1.70bn
Scenario certified
ScenarioSAR 1.20bn
Scenario EAC
ScenarioSAR 2.65bn
Illustrative delivery position
Records are joined by ID across the Asite product set.
| Record | Reference | Status | Captured in | Open |
|---|---|---|---|---|
| Milestone | MS-G-WALDORF-1 · Enabling works completion | at risk · forecast 19 Jan 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-WALDORF-2 · Primary structure topping out | on track · forecast 12 Dec 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-WALDORF-3 · Facade first panel installed | on track · forecast 3 Mar 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-WALDORF-4 · MEP first fix complete | slipping · forecast 7 Dec 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-WALDORF-5 · Vertical transportation energisation | on track · forecast 27 Jan 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-WALDORF-6 · Landscape hard works complete | at risk · forecast 13 May 2027 | Asite PMIS | Readiness |
| Document | DOC-WALDORF-100 · General arrangement plan — level 01 rev A01 | rejected | Asite CDE | Register |
| Document | DOC-WALDORF-101 · Structural frame details — grid F rev B02 | rejected | Asite CDE | Register |
| Document | DOC-WALDORF-102 · MEP services coordination model extract rev C03 | rejected | Asite CDE | Register |
| Document | DOC-WALDORF-103 · Facade bracket and anchor details rev A04 | rejected | Asite CDE | Register |