Diriyah 1 — hospitality cluster
Four Seasons Hotel & Private Residences, Diriyah
The published section below is public fact with a source. Everything in the delivery section is an illustrative demonstration record.
Published project investment value
Public factSAR 3.10bn
Includes land and construction. Not a construction award and not comparable with award values.
Announced
Public fact7 Jan 2026
Announcement date as published.
Named child assets
Public fact2
Children of one parent award. None carries an independent published budget.
Illustrative records joined here
Scenario30
Across schedule, documents, field, commercial, procurement and risk.
Published scope and parties
- SAR 3.1bn is a total project investment value including land and construction — it is not a construction award
- 159-room hotel
- Project area 235,938 sqm
Parties as publishedMidad Development and Real Estate Investment Company (joint development agreement)
Child assets
Named components of the parent award. Values are never split or invented for children.
| Asset | Treatment | Independent budget |
|---|---|---|
| 159-room hotel | Published scope component; no separate value. | None published |
| Private residences | Published scope component; no separate value. | None published |
Illustrative cashflow shape
Scenario planned versus recorded actual. Demonstration values only.
Scenario control budget
ScenarioSAR 3.10bn
Scenario committed
ScenarioSAR 1.93bn
Scenario certified
ScenarioSAR 795m
Scenario EAC
ScenarioSAR 3.19bn
Illustrative delivery position
Records are joined by ID across the Asite product set.
| Record | Reference | Status | Captured in | Open |
|---|---|---|---|---|
| Milestone | MS-G-FS-1 · Enabling works completion | at risk · forecast 20 Feb 2028 | Asite PMIS | Readiness |
| Milestone | MS-G-FS-2 · Primary structure topping out | at risk · forecast 14 Oct 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-FS-3 · Facade first panel installed | on track · forecast 16 Oct 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-FS-4 · MEP first fix complete | on track · forecast 13 Jun 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-FS-5 · Vertical transportation energisation | slipping · forecast 14 Feb 2028 | Asite PMIS | Readiness |
| Milestone | MS-G-FS-6 · Landscape hard works complete | on track · forecast 21 Feb 2028 | Asite PMIS | Readiness |
| Document | DOC-FS-100 · General arrangement plan — level 01 rev A01 | approved with comment | Asite CDE | Register |
| Document | DOC-FS-101 · Structural frame details — grid F rev B02 | approved | Asite CDE | Register |
| Document | DOC-FS-102 · MEP services coordination model extract rev C03 | under review | Asite CDE | Register |
| Document | DOC-FS-103 · Facade bracket and anchor details rev A04 | approved | Asite CDE | Register |