Diriyah 1 — Diriyah Square
Diriyah Square — retail package
The published section below is public fact with a source. Everything in the delivery section is an illustrative demonstration record.
Published construction award
Public factSAR 2.25bn
As announced; not a live approved budget.
Announced
Public fact14 Jul 2025
Announcement date as published.
Named child assets
Public fact2
Children of one parent award. None carries an independent published budget.
Illustrative records joined here
Scenario38
Across schedule, documents, field, commercial, procurement and risk.
Published scope and parties
- 400 retail units across 73 buildings
- 365,340 sqm reported in the Diriyah September 2025 summary
- Package 3 — finishing and MEP scope per the contractor's primary release
Parties as publishedSalini Saudi Arabia (Webuild)
Child assets
Named components of the parent award. Values are never split or invented for children.
| Asset | Treatment | Independent budget |
|---|---|---|
| 400 retail units | Published scope component; no separate value. | None published |
| 73 buildings | Published scope component; no separate value. | None published |
Illustrative cashflow shape
Scenario planned versus recorded actual. Demonstration values only.
Scenario control budget
ScenarioSAR 2.25bn
Scenario committed
ScenarioSAR 1.40bn
Scenario certified
ScenarioSAR 621m
Scenario EAC
ScenarioSAR 2.24bn
Illustrative delivery position
Records are joined by ID across the Asite product set.
| Record | Reference | Status | Captured in | Open |
|---|---|---|---|---|
| Milestone | MS-SQ-01 · Mall-wide finishes material approval | at risk · forecast 7 Nov 2026 | Asite PMIS | Readiness |
| Milestone | MS-SQ-02 · Heritage stone cladding mock-up sign-off | at risk · forecast 21 Nov 2026 | Asite PMIS | Readiness |
| Milestone | MS-SQ-03 · Retail unit handover tranche 1 (120 units) | at risk · forecast 22 Apr 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-SQUARE-1 · Enabling works completion | on track · forecast 19 Dec 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-SQUARE-2 · Primary structure topping out | slipping · forecast 15 Apr 2027 | Asite PMIS | Readiness |
| Milestone | MS-G-SQUARE-3 · Facade first panel installed | on track · forecast 15 Jun 2027 | Asite PMIS | Readiness |
| Document | DOC-SQ-ARC-118 · Diriyah Square — external stone cladding specification rev B02 | under review | Asite CDE | Register |
| Document | DOC-SQUARE-100 · General arrangement plan — level 01 rev A01 | rejected | Asite CDE | Register |
| Document | DOC-SQUARE-101 · Structural frame details — grid F rev B02 | approved | Asite CDE | Register |
| Document | DOC-SQUARE-102 · MEP services coordination model extract rev C03 | approved | Asite CDE | Register |